Highlands Ranch Road Improvements

 Travel Planning Made Easier for Highlands Ranch Drivers

County collaborates with CDOT to embed intersection images on COTRIP.ORG site

If you’re one of the thousands of drivers who frequently use major roads within Highlands Ranch and northern Douglas County you now have a new way to evaluate traffic conditions before you travel.

Through a collaboration with the Colorado Department of Transportation (CDOT), 33 County intersections have been added to the department’s website. Visit CDOT’s link www.cotrip.org/device.htm, zoom in, and select one of the County’s 33 regularly-updated still cameras in Highlands Ranch and northern Douglas County, as well as 29 CDOT locations along the I-25 and C-470 corridors within Douglas County.  Additional locations will likely be added in the near future.

The camera snapshots are updated every 15 minutes, allowing drivers who travel the County’s most frequently-used roadways the ability to scan conditions 24-hours a day, 365 days a year.


Highlands Ranch Roadway Cone Zone / Lane Closure / Sidewalk Repair Schedule

Highlands Ranch Contracted Roadway Projects

For detailed information on specific projects, please click on the links listed above or below or visit www.cotrip.org 

Quebec / Lincoln / University Improvement Project

This is a multi-phase operational and maintenance project that focuses on improvements and approaches to this intersection. The first phase of this Project focused on rebuilding the existing concrete pavement. Approximately 10,000 square yards of existing concrete pavement were replaced. The first phase of construction was completed in Spring 2013. The second phase of the Project will focus on improving the northbound right-turn lane from Quebec Street to Lincoln Avenue and the acceleration lane on EB Lincoln Avenue, widen Lincoln Avenue for future EB lane and fix vertical grade issue that exist on the southeast corner of the intersection.

The roadway improvements for this second phas started in June 2016 and are expected to be completed in the fall of 2016, with irrigation and landscaping completion for the spring of 2017.  Future phases fo the project will focus on widening of other legs of the intersection in order to provide for additional capacity improvements.  The current temporary barrier located at Dutch Creek Street and Quebec will remain until Phase 2 is completed and the traffic has stabilized at the Lincoln Avenue / Quebec intersection (no sooner than Fall 2016)Final design and ROW have been completed and utility relocation are ongoing.   The Improvements started in June and are expected to be completed in the Fall of 2016.   Other future phases of the Project will focus on widening of other legs of the intersection in order to provide for additional capacity improvements. The current temporary barrier located at Dutch Creek Street and Quebec will remain there until the Phase 2 project is completed and the traffic has stabilized at the Lincoln Avenue / Quebec intersection (no sooner than Fall 2016).

For further information about construction and utility relocation schedule, please contact Dennis Lobberding at QuebecLincoln@douglas.co.us.

Curb, Gutter and Sidewalk Repair

The 2016 Curb, Gutter and Sidewalk Repair projects will be occurring throughout Highlands Ranch.  These repair projects are only for locations listed in the map above.  This project replaces substandard adjacent curb and gutter, concrete cross-pans, installs required ADA ramps in advance of planned worked for Asphalt Overlay Roadway Projects and Concrete Pavement Repair Projects.

If you have questions about repairing a curb, gutter or sidewalk that is outside of the area on the map, please contact Public Works Operations via the online form.

For further information please contact Keith Burke, Public Works Engineering at SurfaceTreatment@douglas.co.us