Updated August 19, 2025
This project has been completed.
Completed
Updated August 19, 2025
This project has been completed.
Douglas County’s 2025 neighborhood street paving program in Bell Cross Ranch includes Bell Cross Circle, Bell Cross Way, Roy Clarke Boulevard, and Mary Clarke Place.
On each street, work will be completed in phases – the first phase consisted of sidewalk repairs and curb ramp upgrades, which will be performed by the County’s sidewalk repair contractor. Sidewalk repairs usually take between two and four weeks per neighborhood to be completed; work on a single block will generally take three to four days.
The second phase occurred later in the summer and consisted of rotomilling to remove some of the top layer of asphalt, which generally takes two to four hours or less per block to complete and was performed by the County’s asphalt overlay contractor. The final phase followed rotomilling by one to two weeks and included placing the new overlay; this last phase typically took 4 – 8 hours per block to complete.