This project has been completed.
Douglas County’s 2025 street paving program includes East Palmer Divide Avenue from Furrow Road to Hwy 83. This project will be utilizing high performance asphalt to extend the life of the new surface.
Work will be completed in phases – the first phase consists of rotomilling to remove some of the top layer of asphalt, which generally takes two to four hours or less per block to complete and will be performed by the County’s asphalt overlay contractor. The final phase follows rotomilling by one to two weeks and includes placing the new overlay; this last phase may take 4 – 8 hours per block to complete.