Updated April 19, 2024
Construction operations have started again (end of March 2024) after a winter shutdown.
See “Schedule Section” below for further information.
Under Construction
Updated April 19, 2024
Construction operations have started again (end of March 2024) after a winter shutdown.
See “Schedule Section” below for further information.
Douglas County is improving Bayou Gulch Road between Pradera Parkway and Scott Avenue by realigning the roadway, installing new asphalt pavement, improving the storm infrastructure, and installing a continuous sidewalk throughout the project. After construction, the entire road – from Pradera Parkway to Scott Avenue – will have one lane in each direction paved with new asphalt, three-foot shoulders, and a continuous concrete sidewalk for pedestrian access.
This project also includes:
April 20-30, 2024:
The top mat of asphalt was placed on April 12, and striping operations are expected during the week of April 22 (weather dependent). The few remaining items include final seeding and mulching, rock mulch placement, and final punch list items.
Construction started on June 26, 2023, and is expected to be completed in May 2024. Working hours are 7 a.m. to 6 p.m., Monday through Friday. Occasional Saturday work is possible but must be approved by Douglas County Public Works. There will be no work during the holidays.
Road Closures:
Bayou Gulch Road will be CLOSED in different roadway sections within two different phases of the project, as follows: