Updated September 26, 2025
This project is now complete! The full closure opened ten days earlier than expected on the morning of Thursday, Sept. 25, 2025.
Completed
Updated September 26, 2025
This project is now complete! The full closure opened ten days earlier than expected on the morning of Thursday, Sept. 25, 2025.
Phase 1 of the Grigs Road Paving Project involves the extension of the existing asphalt pavement from Daniels Park Road to the East/West Regional Trailhead & Pavilion parking lot.
Currently, this section of Grigs Road has a gravel road surface and has roadside ditches on both sides for drainage purposes.
The project will span 1 mile in length and will require significant earthwork, the installation of new curb and gutter, and the construction of six-inch asphalt pavement. Additionally, drainage enhancements will be implemented throughout the installation of eight (8) new inlet structures. The existing metal pipe culvert crossings will be replaced with upgraded reinforced concrete pipes and flared-end sections.