Updated July 10, 2025
Pre-Construction work will occur during the week of July 14 – 18, 2025, from 8:30 a.m. to 7 p.m. which will include tract cleaning of the outfall of the pipe in preparation for construction to officially begin on July 21, 2025. Once construction begins, drivers will experience major traffic shifts during construction. East and westbound traffic will be reduced down to one (1) lane each direction and it will shift to either be all in the eastbound lanes and then once we get through the median it will be one (1) lane each direction but in the westbound lanes. Work hours are from (approximately) 7 a.m. to 9 p.m., Monday through Saturday.
This project is anticipated to be completed by August 6, 2025, weather dependent.