Completed
Updated July 1, 2025
As of June 30, 2025, Phase 3 of construction has been completed, and the road has been reopened. Construction started on May 5, 2025. The road construction included the installation of new culverts, grading, and asphalt paving for this gravel road section of Palmer Divide Avenue.
Currently, the Contractor is working on the final punch list work, so there may be traffic control in the area, and possible lane closures with flaggers.
The Palmer Divide Avenue Paving Project Phase 3 consists of extending the existing E. Palmer Divide Avenue asphalt pavement from approximately 660′ west of Phoebe Grove to approximately 230′ east of S. East Cherry Creek Road. This section of the roadway is currently paved in gravel.
E. Palmer Divide Avenue lies on the southern boundary of Douglas County. This section of E. Palmer Divide Avenue is currently maintained by Douglas County. This project will also include drainage improvements by replacing five (5) existing culvert crossings with new reinforced concrete pipe and flared end sections.