Updated September 15, 2023:
Project timelines have changed – please see “Schedule” section below for more information.
Planning/Design
Updated September 15, 2023:
Project timelines have changed – please see “Schedule” section below for more information.
Proposed improvements:
The proposed improvements will improve the safety of traffic operations and reduce congestion. The design plans are about 60 percent complete. They are now being finalized as IREA has determined how they will move forward with relocating their existing facilities along Pine Lane that are in conflict with the proposed improvements. IREA’s construction schedule must be delayed to provide them with adequate time to obtain several permanent easements.