Alert

In observance of Memorial Day, County offices will be closed Monday, May 30. For online services, visit our web page.

×

01.

Help Me With...

Select from list
My Residential Property
My Driver's License or Vehicle Registration
Requesting Assistance
Getting Outdoors
Elections

02.

Select from list
My Property Valuation
Understanding My Valuation
Paying My Property Tax
Neighborhood Sales
Building Permits
Vehicle Registration - New Stickers
Vehicle Registration - New Vehicle
Drivers License - New or Renew
New Resident Vehicle Registration
Adult Protection
Child Welfare
Child Support
Child Care
Financial Assistance
Medical Assistance
Food Assistance
Decode Douglas County
Open Space Special Event Permits
Open Space Properties and Trails
Park Reservations
Parks and Trails
Register to Vote / Update Voter Registration
Upcoming Election Information
Ballot Drop Box Locations
Voter Service and Polling Centers

03.

×
× Close
Public Works

Pine Lane Widening Project

Planning/Design

Budget

The project is estimated to cost approximately $1.6 million

Project Manager

Art Griffith, P.E.
[email protected]

303-660-7490

Description

This Project will widen Pine Lane from a 2-lane roadway section (one through lane in each direction) to include a center two-way left-turn lane between Dixon Drive and Pine Drive as well as provide a westbound right-turn deceleration lane at Dixon Drive. The project will improve safety, traffic operations, and reduce congestion. The design plans are about 60 percent complete and are now being finalized as IREA has determined how they will move forward with relocating their existing facilities along Pine Lane that are in conflict with the proposed improvements. IREA’s construction schedule needs to be delayed to provide them with adequate time to obtain several permanent easements.

Schedule

This project will be constructed at the same time as the Pine Drive Project.

  • 2021 – Complete final design spring 2022
  • 2022 – Complete ROW acquisitions, including easements by utility companies by summer 2022
  • 2022 – Anticipate IREA will complete its relocation by spring 2022
  • 2022 – County to begin construction in late 2022 and at the same time as the Pine Drive Project

Project Manager
Art Griffith, P.E.
[email protected]
303-660-7490