Updated July 23, 2025
- Lakeshore Drive (between Tempest Ridge & Lakewood Drive) Storm Sewer System Installation: Work will begin on July 23, 2025, and is anticipated to be completed on August 29, 2025, weather dependent. During this storm sewer system installation, construction will occur Monday through Friday, 7 a.m. to 3:30 p.m. Please plan on delays, and traffic will be limited to local traffic only.
- Pinery Outfall Cleaning: Douglas County was successful in cleaning 40 outfalls in 2024 and has extended the program into 2025. We anticipate cleaning an additional 27 outfalls. Work will occur on these outfalls in 2025 in either late winter/early spring, and again in fall/winter after the vegetation has died back due to frost.