01.

Help Me With...

Select from list
My Residential Property
My Driver's License or Vehicle Registration
Requesting Assistance
Elections
Health Department

02.

Select from list
My Property Valuation
Understanding My Valuation
Paying My Property Tax
Neighborhood Sales
Building Permits
Vehicle Registration - New Stickers
Vehicle Registration - New Vehicle
Drivers License - New or Renew
New Resident Vehicle Registration
Adult Protection
Child Welfare
Child Support
Child Care
Financial Assistance
Medical Assistance
Food Assistance
Register to Vote / Update Voter Registration
Upcoming Election Information
Ballot Drop Box Locations
Voter Service and Polling Centers
Birth Certificates
Community Health
Death Certificates
Environmental Health
Household Waste Management
Public Health Services

03.

×
× Close
Public Works

Pine Gulch Dam Project

Dams

Budget

Estimated Total = $1.0 Million

Project Manager

Zak Humbles, P.E.
[email protected]douglas.co.us

303-660-7490

Contractor

Hudick Excavating, dba HEI Civil

Project Update

Updated November 22, 2022: 

The Pine Gulch Dam project was awarded to the contractor, Hudick Excavating, on April 12, 2022 by the Douglas County Board of County Commissioners. Currently, utility contractors are undergrounding facilities which are currently located overhead – in order to move forward with construction.  Earthwork is anticipated to begin in late December 2022 (see “Schedule” section below for more information).

Description

FP-P1 Pine Gulch Dam: This project will reduce the hazard classification and risk of the dam by converting it to a non-jurisdictional structure, as well as maintaining the current flood protection it provides. This will entail reshaping the pool area from a steep and deep pool, to a broad and shallow pool.

For coordination and communication purposes, property owners adjacent to the dam and within the easement can contact Zachary Humbles at 303-660-7490 or [email protected]

Schedule

From October through December 2022, utility contractors are undergrounding facilities that are currently located overhead. Earthwork will start in December 2022, with the anticipated completion date of the project to occur in early spring 2023.

Project Manager
Zachary Humbles, P.E.
[email protected]
303-660-7490