Change in Start Date for Asphalt Overlay: Starting on August 7, 2024, Brannan Gravel & Sand (Contractor) will begin the asphalt overlay on these same residential streets (locations mentioned above) with an anticipated project duration of 10 calendar days from notice to proceed start date.
Sidewalk Repairs will start on residential streets in the Roxborough area surrounding Liverpool Circle and Hunters Hill Lane, after July 1, 2024 (start date TBD). These repairs will be completed approximately in 15 calendar days from notice to proceed start date. The contractor is Chatos Concrete.