Alert

Douglas County Government offices closed Monday, July 5Continue Reading

Highlands Ranch Neighborhood Paving

Project Description

The 2021 neighborhood street paving program in Highlands Ranch includes streets in the Northridge, Ranch Road, Thistle Ridge, and Kentley Hills areas.  See the 2021 Neighborhood Street Paving Map for specific locations.

On each street, work will be done in two phases – the first phase consists of rotomilling to remove some of the top layer of asphalt, which generally takes 2 to 4 hours or less per block to complete.  Phase 2 follows a week or two later and includes placing the new overlay; this phase may take 4 – 8 hours to complete.  During construction, access to driveways is allowed, with occasional short delays.

Two days before the start of construction, no-parking signs are posted along the streets scheduled for work.  Construction will be performed Monday through Friday between 7 a.m. – 7 p.m.  Work will be scheduled between July and November.

Schedule

Sidewalk repairs in Highlands Ranch are scheduled to begin in August and be complete by the end of September.  Paving is scheduled to begin the middle of September and be complete by the end of October.

Contractor
Martin Marietta Materials, Inc.
Project Manager: Brian Ruddell
Phone: 303-410-5739
[email protected]

Project Inspector
Keith Burke
Phone: 303-947-8720
[email protected]

FAQs

My vehicle was towed because it was left in the construction zone.  How do I find out where it went?
Please contact Westside Towing at 303-688-5244 for information on where your car was towed.

For all other issues, contact Dan Roberts, Project Engineer for Douglas County Public Works Engineering at [email protected] or 303-663-6284.