Alert

Stage 2 Fire Restrictions in place for Unincorporated Douglas CountyContinue Reading

Stonegate Neighborhood Paving Projects

 

 Douglas County takes COVID-19 seriously and will ensure our contractors follow appropriate health and safety practices as recommended by the Association of General Contractors (AGC) and Colorado Contractors Association (CCA)

 

Project Description

The 2020 neighborhood street paving program in Stonegate includes streets south of Chaparral High School, and streets on both sides of Keystone Boulevard south of Lincoln Avenue.  See the 2020 Stonegate Neighborhood Street Paving Map for specific locations.

On each street, work will be done in two phases – the first phase consists of rotomilling to remove some of the top layers of asphalt, which generally takes 2 to 4 hours or less per block to complete.  Phase 2 follows a week or two later and includes placing the new overlay; this phase may take 4 – 8 hours to complete.  During construction, access to driveways is allowed, with occasional short delays.

Two days before the start of construction, no-parking signs are posted along the streets scheduled for work.  Construction will be done Monday through Friday between 7 a.m. – 7 p.m.

Schedule

Work on the 2020 program will begin May 11 and be completed by the end of October.  View the weekly schedule to see where paving work is scheduled for the week.

Contractor

Martin Marietta Materials, Inc.
Project Manager: Brian Ruddell
Phone: 720-926-2160
[email protected]

Project Inspector
Brian Schultz
Phone: 303-947-8721
[email protected]

FAQs

My vehicle was towed because it was left in the construction zone.  How do I find out where it went?
Please contact Westside Towing at 303-688-5244 for information on where your car was towed.

For all other issues, contact Dan Roberts, Project Engineer for Douglas County Public Works Engineering at [email protected] or 303-660-7487.